BCP's Local Plan was thrown out in 2025 and the replacement is not due until January 2029. What decides applications meanwhile, and when you can comment.
The biggest planning story in Bournemouth is not a single scheme. It is that the council has no up-to-date Local Plan, will not have one until 31 January 2029 at the earliest, and is deciding every application in the meantime against policies written for a council that no longer exists.
That is not a complaint about BCP. It is the council’s own published position. Here is how it happened, what happens next, and the two dates on which your opinion counts.
The plan that failed
BCP Council submitted a draft Local Plan for examination in June 2024. Two government-appointed Inspectors held Stage 1 hearings in January 2025 and on 6 March 2025 the council confirmed they would not support it.
The arithmetic behind that is stark, and it is set out in a report to Dorset Council’s Cabinet on 15 October 2024. The Government’s standard method put BCP’s Local Housing Need at 2,806 new homes a year. BCP’s submitted plan proposed an average of 1,600 a year, which the report describes as 1,206 homes a year short. Across the 2024 to 2039 plan period that came to an unmet need of more than 15,000 homes, and BCP formally asked Dorset Council to take some of it. Dorset’s Cabinet report concluded it was unlikely to be able to meet any of it.
That is what sank the plan. The Inspectors’ problem was not only the number, it was the Duty to Cooperate: the legal requirement to sort cross-boundary housing out with your neighbours before you submit, not after.
The same Dorset report notes that under the standard method then being proposed, BCP’s figure would rise to 2,962 homes a year.
Cllr Millie Earl, the Leader of BCP Council, said at the time: “We are disappointed with the Inspectors’ response to our Local Plan submission.” The council’s case has been that its coastal location, waterways and protected habitats limit how much land it can build on, and that national infrastructure investment is needed alongside any target.
On 7 May 2025 the council announced it would withdraw the draft and start again. Cllr Earl said: “Whilst we are disappointed that the outcome from examination means our draft Local Plan has to be withdrawn, I am confident that the preparation that we have already undertaken remains highly relevant and can be used to inform our new Local Plan.”
The new plan, and the two dates that matter
BCP is now preparing a fresh Local Plan under the Government’s new plan-making system, and has published a statutory timetable for it. The notice of intention to commence was published on 3 June 2026.
| Stage | Date |
|---|---|
| Notice to commence plan making | 3 June 2026 |
| Scoping consultation opens | 15 June 2026 |
| Scoping consultation closes | 27 July 2026 |
| Gateway 1 self-assessment | 3 October 2026 |
| Plan content and evidence consultation | 19 October to 27 November 2026 |
| Gateway 2, Planning Inspectorate assessment | 5 April 2027 |
| Proposed Local Plan consultation | 27 September to 19 November 2027 |
| Gateway 3, Planning Inspectorate assessment | 17 March 2028 |
| Plan submission | 26 May 2028 |
| Plan adoption, indicative | 31 January 2029 |
The scoping consultation closed on 27 July 2026, so if you missed it, you missed it. The next window opens on 19 October 2026 and runs for six weeks, and it is the one where the council asks about the spatial strategy, the evidence and any draft policies. In practical terms it is the stage at which the shape of the plan is still arguable. By the time the proposed plan goes out in autumn 2027, the question narrows to whether the plan is sound.
The council runs a Local Plan mailing list and takes questions at BCPlocalplan@bcpcouncil.gov.uk.
118 sites are already on the table
Alongside the plan, the council has been running a Call for Sites, which is where landowners, developers and site promoters put land forward for consideration. The 2025 round, between 10 July and 29 August, brought in 118 site submissions, and the council has published them on an interactive map with the address, area, proposed use and a reference number for each.
The Call for Sites reopened for six weeks from 15 June to 27 July 2026.
Two things are worth understanding about that map. First, publication is not endorsement: the council states plainly that no site has been assessed and no decision has been made on any of them. Second, and less comfortably, the council notes that some submissions may have been made by promoters without the landowner’s permission, and invites landowners with concerns to get in touch. If a field or car park near you is on that map, that is the first thing to check.
What is deciding applications in the meantime
Until the new plan is adopted, planning applications in Bournemouth are judged against a development plan that predates BCP Council entirely:
- the Bournemouth Core Strategy (2012)
- the Bournemouth Town Centre Area Action Plan (2013)
- the Affordable Housing Development Plan Document (2009)
- saved policies from the Bournemouth District Wide Local Plan of 2002
- the Boscombe and Pokesdown Neighbourhood Plan
- the joint BCP and Dorset Minerals and Waste Plans
There is also an Article 4 Direction on houses in multiple occupation, in force since December 2011, covering the whole of the Bournemouth area and Talbot Village in Poole. It means you need planning permission to turn a house into a small HMO of three to six unrelated people sharing amenities, which in a town with two universities is one of the most frequently used policies on the list.
What the committee actually decides
Most people picture planning as a committee. In Bournemouth it very largely is not. The council operates two area committees, Eastern and Western, and they see only the applications that are called in or are large or contentious. Everything else is decided by officers under delegated powers.
The scale of that is easy to miss until you read a set of minutes. At its meeting on 25 June 2026, the Eastern BCP Planning Committee considered three applications and finished in 49 minutes:
- 5 Seafield Road, Southbourne (P/26/00686/FUL): demolish a house and garage and build a block of six flats with off-road parking. Granted, unanimously.
- 44 Minterne Road, Christchurch (P/26/01738/CONDR): variation of conditions on an approved house remodelling. Granted, unanimously.
- 46 South Road, East Cliff (P/26/02127/HOU): a retrospective application for a lean-to over a rear patio. Granted, unanimously.
The first of those is the pattern of Bournemouth development in a single line: one house replaced by six flats. It is why 42% of everything sold in the town is a flat, a figure we get to on our Bournemouth house prices page, and it is happening one street at a time rather than through a plan.
The July committee was cancelled. The next Eastern meeting is 20 August 2026 at the Civic Centre on Bourne Avenue, and agendas are published the week before.
How to check and comment on an application
The live planning register is at planning.bcpcouncil.gov.uk, which is where applications, documents, consultation dates and decisions are published. Be aware that a plain visit lands on a disclaimer page first.
References that begin P/26/ are the current numbering. The older 7-2024- style references belong to the pre-merger Bournemouth series and still turn up on long-running schemes.
If you want to speak at committee, requests must reach Democratic Services by 10am on the working day before the meeting. Objectors share a combined five minutes and supporters share another five, with no single speaker taking more than two and a half minutes unless nobody else has registered. You can submit a written statement of up to 450 words instead, which is read out on your behalf. That is separate from, and does not replace, a written representation made during the application’s consultation period.
Frequently asked questions
Does Bournemouth have a Local Plan?
Not a current one. BCP Council withdrew its draft Local Plan in May 2025 after Inspectors declined to support it, and the replacement is not due to be adopted until 31 January 2029 at the earliest. Applications are meanwhile decided against the Bournemouth Core Strategy of 2012 and saved policies from 2002.
Why was the BCP Local Plan rejected?
Inspectors concluded at Stage 1 of the examination, in March 2025, that they could not support it. The central problems were the Duty to Cooperate and a housing target of 1,600 homes a year against an assessed need of 2,806, leaving more than 15,000 homes unmet over the plan period that neighbouring Dorset Council said it was unlikely to be able to absorb.
How many homes does Bournemouth have to build?
The Government’s standard method put BCP’s Local Housing Need at 2,806 homes a year when the last plan was examined, rising to 2,962 under the revised method then being proposed. The withdrawn plan offered 1,600 a year.
When can I comment on the new Local Plan?
The next consultation runs from 19 October to 27 November 2026 on the plan’s content, evidence and spatial strategy. After that there is one more, on the proposed plan itself, from 27 September to 19 November 2027.
How do I find planning applications near me in Bournemouth?
Search the council’s register at planning.bcpcouncil.gov.uk. It carries the documents, the consultation deadline and the decision for each application.
Has a site near me been put forward for development?
Possibly. The 2025 Call for Sites brought 118 submissions, all published on the council’s interactive map. A site being on the map means only that somebody has offered it, not that the council has assessed or accepted it.
Sources
- BCP Council, BCP Local Plan and Community Infrastructure Levy and its Local Plan timetable and Call for Sites pages.
- BCP Council, an update on the examination of BCP Council’s Local Plan, 6 March 2025 for the Inspectors’ conclusion and the Earl quote.
- BCP Council, BCP Council to begin work on new Local Plan, 7 May 2025 for the withdrawal and restart.
- Dorset Council Cabinet, BCP Council unmet housing need response, 15 October 2024 for the 2,806 and 2,962 standard-method figures, the 1,600 target and the 15,000-home unmet need.
- BCP Council, current Local Plans for the Bournemouth area for the policies still in force and the Article 4 HMO direction.
- Eastern BCP Planning Committee, minutes of 25 June 2026 for the applications decided and the public speaking rules.
- BCP Register, planning applications for live applications and decisions.
Checked 9 August 2026. Timetables published under the new plan-making system are statutory but can be revised, so confirm the current dates on the council’s own timetable page before relying on them. What all this means for prices is on Bournemouth house prices; what it means for the roads is on Bournemouth roadworks and travel.
Have your say
We read every message. To comment on this story, email the newsdesk and we may publish a selection of responses: hello@bournemouthpost.co.uk.