Muscliff Park reopened on 12 November, after Kings Park and Churchill Gardens. Noyce Gardens and Anchor Close are due back in mid-November. Updated November 2026.

Updated 15 November: BCP’s concept plans page, updated 12 November, lists Muscliff Park as completed and reopened on 12 November. Noyce Gardens has moved again, to mid-November, and Anchor Close in Kinson is also due back in mid-November. In Poole, Green Road in the Old Town is listed as completed and reopening on 13 November.

Updated 5 November, evening: Churchill Gardens phase 1 reopened on 5 November, a day ahead of its 6 November date, with a climbing frame, spinning dish, rope swing and slingshot rotator (our story). The council’s concept plans page now gives Noyce Gardens as due in early November, not end of October.

Updated 5 November: BCP’s concept plans page, updated 4 November, still lists Noyce Gardens as due end of October and Muscliff Park as early November. Three more upgrades, including Anchor Close in Kinson, were announced on 3 November.

Updated 2 November: BCP’s concept plans page, updated 30 October, now lists Kings Park on Ashley Road as completed and reopened on 30 October, a day later than its last date and the Friday of half term. Noyce Gardens is still shown as “end October” with no reopening recorded. Muscliff Park is due in early November and Churchill Gardens phase 1 on 6 November. Anchor Close in Kinson is still listed as “scheduled to start on site 26 October”, due mid-November.

Updated 26 October: BCP’s concept plans page, updated 22 October, has moved Kings Park on Ashley Road from 23 to 29 October, so it stays shut for most of half term. Noyce Gardens is still due at the end of October and Muscliff Park in early November. Anchor Close in Kinson is due on site today. In Poole, Hatchards Field reopened on 21 October.

Updated 19 October: BCP’s concept plans page, updated 16 October, says Mallard Road was completed and reopened on 9 October. Kings Park at Ashley Road is now due on 23 October. Noyce Gardens has moved for a third time, to the end of October, and Muscliff Park to early November. Churchill Gardens phase 1 started on 12 October and is due on 6 November; the toddler zone, games area and café stay open. Anchor Close in Kinson (BH11 9HZ, £60,000) is due on site on 26 October and back by mid-November. The table and graphic below show the new dates. The council confirmed the Muscliff and Churchill Gardens starts on 16 October.

Two more Bournemouth play areas have been added to BCP Council’s rebuilding programme. Setley Gardens, behind Castlepoint, gets what the council calls a full refurbishment, and Chesildene Avenue gets repairs, both announced on Thursday 17 September after a consultation in June.

Neither announcement carries a figure or a date. What the council has published dates for is the rest of the autumn, and by the second week of October five Bournemouth play areas will have contractors on them at the same time.

The five Bournemouth sites, and when the council says they finish

These are the dates and budgets on BCP Council’s own Plan for Play concept plans page, as updated on 12 November.

Bournemouth play area rebuilds with published budgets and dates, from BCP Council's Plan for Play concept plans page, updated 12 November 2026
SiteTypeBudgetOn siteAnticipated completion
Kings Park, Ashley Road, BH1 4NNReplacement£186,2001 SeptemberReopened 30 October
Noyce Gardens, BH8 0JZReplacement£181,5009 SeptemberMid-November
Mallard Road, BH8 9PJRefurbishment£104,00010 SeptemberReopened 9 October
Muscliff Park, Shillingstone Drive, BH9 3LRRefurbishment£134,70029 SeptemberReopened 12 November
Churchill Gardens, BH1 4ESPhase 1 of a phased scheme£60,00012 OctoberReopened 5 November
Anchor Close, Kinson, BH11 9HZRefurbishment£60,00026 OctoberMid-November

The first five sites add up to £666,400, and Anchor Close takes the total to £726,400. Four have reopened: Mallard Road, Kings Park, Churchill Gardens phase 1 and Muscliff Park. Kings Park came back on 30 October, the Friday of half term, which runs from 26 to 30 October. Noyce Gardens, first due at the end of October, is now listed for mid-November, the same as Anchor Close.

Two more are running in Poole over the same period: Hatchards Field on Rossmore Road went on site on 14 September with £103,500 and reopened on 21 October, and Hamworthy Park started on 12 October with £187,900 and a completion date of 23 December.

Timeline of five Bournemouth play area rebuilds, September to November 2026 Kings Park ran from 1 September and reopened on 30 October. Noyce Gardens runs from 9 September to the end of October. Mallard Road ran from 10 September and reopened on 9 October. Muscliff Park runs from 29 September to early November. Churchill Gardens phase 1 runs from 12 October to 6 November. Five Bournemouth play areas: one reopened, four still on site Start on site and anticipated completion, as published by BCP Council on 22 October 2026. today 1 Sep1 Oct1 Nov1 Dec Kings Park, Ashley Road Noyce Gardens Mallard Roadreopened 9 Oct Muscliff Park Churchill Gardens, phase 1 Source: BCP Council, Plan for Play concept plans, updated 22 October 2026. "End of October" and "early November" are drawn as 31 October and 7 November. Graphic by The Bournemouth Post
Mallard Road reopened on 9 October. Kings Park reopened on 30 October. The bars show the dates in the council's 22 October update. Noyce Gardens, Muscliff Park and Churchill Gardens are still to finish. Graphic by The Bournemouth Post

Noyce Gardens has already slipped, and two council pages disagree

When we first wrote up the programme on 17 August, the council’s concept plans page said Noyce Gardens would go on site on 21 August and be finished by the end of September. The same page now says it went on site on 9 September with an anticipated completion of mid-October: nineteen days late to start, and about a fortnight later to finish.

There is a second problem with the Noyce date. The council’s news release of 14 September says the work “is expected to take around six to eight weeks”. From a 9 September start, six weeks ends on 21 October and eight weeks ends on 4 November. Neither is mid-October. The two pages were published on the same day.

On 16 October the same page moved Noyce Gardens again, to the end of October. That is the third completion date it has published for the site.

The council has not explained any of the changes. If Noyce Gardens is your local playground, the mid-October date would get it open in time for half term and the six to eight weeks would not. On the record so far, plan for the later one.

Setley Gardens and Chesildene Avenue

Setley Gardens is the bigger of the two announcements. The council says it will get “a full refurbishment that puts the play area back at the heart of the local community”, with the investment “focussed at Setley”.

Chesildene Avenue is the more interesting one. The council’s release says the site “had previously been proposed for repurposing”, which in the council’s own language means taking the equipment out, and that it will now get repairs after “strong local engagement”.

That is not quite the whole sequence. BCP’s Plan for Play page records that the 2025 consultation had already changed Chesildene Avenue’s fate: the “you said, we did” summary from that round says defect repairs would be carried out at Chesildene Avenue, Epiphany School and Knowlton Gardens “until they reach end of life”. The difference now is that the council describes the work as repairs “designed to enhance the existing play offering” rather than keeping a tired site going.

Neither site has a published budget, a design or a date. Both were decided by a consultation held in June 2026, whose results the council has not published in full.

The wider programme is £4.6 million across Bournemouth, Christchurch and Poole, covering around 100 play areas including nearly 20 major refurbishments, paid for from the Community Infrastructure Levy, the charge on new development. Cllr Andy Hadley, the portfolio holder for parks, said the council was investing “to create better, safer and more exciting places for children to play”.

What it means for you

  • Mallard Road is open again from 9 October. Kings Park at Ashley Road, Noyce Gardens, Muscliff Park and Churchill Gardens phase 1 are still behind fences. Anchor Close in Kinson closes from 26 October, the first day of half term.
  • Do not plan half term around a reopening. The council publishes “mid” and “end” of month targets, not dates, and the one site we have tracked from the start has now moved three times.
  • The five sites above are the ones with published designs and dates. The council says dozens of other play areas are getting smaller repairs and new equipment, without naming dates for them. What else is open in the meantime is on our things to do in Bournemouth page.
  • If your play area is still listed for repurposing, the Chesildene Avenue decision shows the list is not fixed. The council says the June consultation “directly shaped how the funding is targeted”.
  • The council posts progress on the Plan for Play news page, which is a different website from the council’s own news hub and is usually the first to carry a start date.