BCP Council wants to re-tender Poole Civic Centre after talks with MCR Property Group failed over its £5.25m offer. Cabinet decides on 25 November.
BCP Council is to put Poole Civic Centre back on the market. Its agreed £5.25m sale to MCR Property Group has not gone through.
A report to Cabinet on 25 November says “it has not been possible to conclude negotiations as MCR want to change the terms of their original offer”. It recommends a fresh tender for the whole listed building and its grounds.
Poole Civic Centre is in Parkstone ward, about four miles west of Bournemouth town centre. The council has already decided to close it as offices and move the staff to its Bournemouth site, the report says.
How the sale got here
The report sets out the timeline:
- 15 October 2024: full Council agreed to sell the former civic centre.
- 24 February to 8 May 2025: the agent, CBRE, marketed it.
- 16 July 2025: Cabinet approved a freehold sale of the whole site to MCR Property Group at £5.25m.
- Since then: the council and MCR negotiated heads of terms and contracts, without agreement.
- 14 October 2026: the council’s cross-party asset disposal working group agreed to sell without the option of leasing part of the building back to Poole Town Council.
That last change matters. The deal with MCR assumed MCR would then offer Poole Town Council a lease on part of the building, known as the “vertical slice”. The report says the town council “now propose to occupy Poole Museum instead”, so that option is no longer needed.
The report says no binding contract or exclusivity agreement was signed with MCR, so the council can walk away. MCR can bid again “on the same basis as other prospective bidders”.
What the council will offer
The report recommends selling on the same basis as last time:
- freehold, not a long lease, to attract the most interest and the biggest receipt
- as one plot, not split into smaller parcels
- sold as seen, not subject to planning permission, because that is “the quickest route” to a sale and to ending the council’s holding costs
The council’s agent will update the brochure and open a data room with environmental and measured surveys, a title report and a planning appraisal. The agent may also advise on overage clauses, which would give the council a share of any later rise in value from development.
Cabinet is asked to recommend that full Council approves the re-tender. It would hand the chief financial officer, in consultation with the finance portfolio holder, Councillor Mike Cox, the power to agree the price and terms.
The risks the council lists
The report names several risks with the site:
- planning, including change of use and conversion of a listed building
- title restrictions on how the site can be used
- trees that have to be kept
- the cost of keeping the listed building’s fabric secure
It also says the site “has been broken into on several occasions, and it attracts antisocial behaviour”.
What it means for you
The money matters more than usual. The council forecasts a £31.7m overspend this year, and selling surplus property is one of the ways it raises cash for capital spending. A delayed sale also means the council keeps paying to secure an empty building.
The report does not say what MCR wanted to change, or whether a new tender is expected to raise more or less than £5.25m. It says the legal work should take at least 12 weeks from accepting an offer, so a sale is unlikely to complete for months.
The building was once part of the council’s regeneration company’s plans. FuturePlaces had planned to turn it into a boutique hotel with some housing, before the council closed the company.
What happens next
The report is on the agenda of the council’s Overview and Scrutiny Board at 6pm on Monday 16 November, before Cabinet on 25 November. If Cabinet agrees, the decision goes to full Council.